2A. C-Bus Toolkit Software
4.1 Project
When first installed, the C-Bus
®
Toolkit contains two example Projects; “CLIPSAL” and “home”.
When a Project folder is selected, the Project window is displayed to the right of the Project Manager
(Figure 9). Functional icons are provided at the top of the Project window. When clicked on, these
perform the functions listed in Table 3.
Figure 9 – The Project window is displayed when a Project folder is selected in the Project Manager
Icon Function
Hide Project Manager Hides the Project Manager, providing more room for the Project window
Add Network Adds a new Network to the current Project. You are prompted to enter a name
and Network connection details.
Delete Project Deletes the selected Project.
Rename Project Prompts you to enter a new name for the selected Project.
Copy Project Creates a copy of the selected Project. You are prompted to type a name.
Close All Networks Closes all open Networks in the selected Project.
Open All Networks Attempts to open all Networks in the selected Project. The relevant Networks must
be connected to the PC via C-Bus for this to be successful.
Backup Project Creates a backup archive of the selected Project. The backup file is given
a sufx of “.cb3” and placed on your Desktop.
Table 3 – Project window icons and their functions